This document is archived and information here might be outdated. Recommended version. |
ArcObjects namespaces > GeoDatabaseDistributed > ESRI.ArcGIS.GeoDatabaseDistributed > Interfaces > IC > ICheckInDataSynchronizer2 Interface (ArcObjects .NET 10.4 SDK) |
Provides access to members that synchronize changes from a check-out geodatabase or delta database with the master geodatabase.
Description | ||
---|---|---|
Synchronize | Synchronizes the changes in the check-out geodatabase or delta database with the master geodatabase. | |
Synchronize2 | Synchronizes the changes in the check-out geodatabase or delta database with the master geodatabase. |
Interfaces | Description |
---|---|
ICheckInDataSynchronizer | Provides access to members that synchronize changes from a check-out geodatabase or delta database with the master geodatabase. |
CoClasses and Classes | Description |
---|---|
CheckInDataSynchronizer | Synchronizes changes from a check-out with the master geodatabase. |
This interface provides Synchronize2 a method to synchronize changes in a check-out. It provides the same functionality as the ICheckinDataSynchronizer::Synchronize method, and additionally allows for specification of how conflicts are defined, detected, and treated during synchronization.
The Synchronize method transfers the changes from a check-out geodatabase (either personal, file, or ArcSDE) or a delta file to the parent replica (previously referred to as the master geodatabase). It does not unregister the check-out.
NOTE: It is recommended that you use ICheckin2 interface to check in changes instead of this interface.